How to Write a Project Progress Report That Supports Decisions

WIT Consultancy

Date Published

A project progress report explains what changed, how delivery compares with the approved plan and which decisions are needed next. Put urgent decisions near the top with an approver, a deadline and the likely consequence of waiting.

A practical progress report template

  1. Reporting period and status date. Say which dates are covered and when the figures were checked.
  2. Summary. Explain what changed and whether key milestones or benefits are at risk.
  3. Milestones and costs. Show the approved target, actual result and forecast. Distinguish commitments, invoices and payments.
  4. Risks, issues and actions. Prioritise items requiring intervention and give each an owner and due date.
  5. Decisions and next steps. Show options, the recommendation, approver and last useful date to decide.

Worked example of a decision request

In a hypothetical fit-out, handover was approved for 18 December. The project now forecasts 23 December because equipment delivery has slipped. The project lead asks the owner to choose by Friday between an illustrative 180,000 XAF for a confirmed local substitute or a five-calendar-day delay. Record the decision and update the forecast after approval.

What does percentage complete mean?

State what the figure measures. Six accepted installations out of ten is 60% by count. Where items vary in size or complexity, use the agreed weighted measure and support it with sign-offs, test results or verified quantities.